The 25 Postponements of NABCO (July to October 2018)

Tomorrow is 1st November 2018 and we expect to be one step closer to working under NABCO.

However, a few people have expressed concerns over the credibility of NABCO and some think NABCO will postpone something else tomorrow.

One of such people is Facebook User Kwabena Sam. He shared the following:

msport-incontent

Why NABCO has lost its credibility just a few months after being launched and that many of us are in doubt about its sustainability.

[We have not even added the postponements from April.]

25 NABCO Postponements in just 3 months

1. Orientation starts from 26th July to 2nd August – Postponed

2. Applicants will be notified about their placements on 28th July – Postponed

3. Successful applicants will start work on 1st August – Postponed

4. Passing out ceremony at various districts on 3rd August – Postponed

5. Successful applicants will start work on 6th August – Postponed

6. Applicants will receive placement notifications on 13th August – Postponed

7. Orientation and Pre-deployment training from 13th August to 30th September – Postponed

8. Verification of ‘Penders’ on 3rd September – Postponed

9. Verification of Pending applicants from 4th to 7th September – Postponed

- Advertisement -

10. Orientation and Training for first batch of successful applicants from 10th to 19th September – Postponed

11. Successful Applicants will be informed about their placements from 10th to 19th September (during orientation) – Postponed

12. Verification of all pending applicants on 11th September – Postponed

13. Orientation of successful applicants from 17th to 19th September – Postponed

14. Verification of ‘Penders’ on 17th September – Postponed

15. District passing out ceremony on 20th September – Postponed

16. Work starts on 1st October – Postponed

17. Regional passing out ceremony on 2nd October – Postponed

18. Trainees will be notified about their placements on 5th October – Postponed

19. NABCO cloth will be available at the districts for collection on 5th October – Postponed

20. Trainees will receive placement notifications on 8th October – Postponed

21. Collection of NABCO cloth on 10th October – Postponed

22. Trainees will be notified about their placements on 15th October – Postponed

23. Work starts on 18th October – Postponed

24. Trainees will be informed about their placements on 17th October at Black Star Square – Postponed

25. Trainees will be paid their first monthly stipend by end of October – Waiting???

I think management should sit up because the initiative is good. We all want to see its success.


Thank you for reading on Asetena.com Share this article with your family and friends.

Follow us on Facebook, Twitter and Instagram for more updates.

Email: [email protected]

Leave a comment